End-to-end project support for establishing a new 200-bed surgical center including equipment procurement, installation, and supply chain setup.
Location
Middle East
Duration
6 months
Project Value
$18M
Status
Completed
Complete turnkey setup of state-of-the-art surgical center with all equipment and supplies, operational within 6 months
Tight project timeline
Complex import regulations
Coordinating multiple equipment categories
Dedicated project management team
Pre-clearance of regulatory requirements
Parallel procurement and installation
Project completed on schedule
200+ equipment items installed
Full regulatory compliance achieved
Operational within target timeline